Marietta Street
The Marietta Street resurfacing project will replace the existing roadway pavement. The project is approximately 1.6 miles long and begins at the intersection of Marietta Street and Howell Mill Road and ends at Park Avenue, the northwestern end of the most recent road repaving and bike lane marking.

A business stakeholder open house for this project was held on August 3, 2017. A formal public meeting was held on August 29, 2017.
  • Project Name: Marietta Street
  • Project Type:
  • Project Start: 04-2016
  • Construction Start: 06-2018
  • Project completion: 12-2018
  • Project Budget: $1,546,210
  • Council District: 3, 4
  • NPU: E,M
  • Complete: 20%